Installation of approximately 2,200 feet of 3ph underground cable, and removal of existing overhead pole line. This project includes the excavation and installation of 2,200 feet of conduit, and the splicing and terminating of the 35kV medium voltage cable. Haugland Energy overhead crews also installed riser poles and overhead lateral feeds to the existing circuits.

The PSNH Power Street included the installation of approximately 1,500 feet of 3ph underground cable, and removal of existing temporary overhead line.