Projects Index

energy Projects

FEMA Long Island Electric Distribution Storm Hardening

FEMA Long Island Electric Distribution Storm Hardening

PSEG Long Island

This $100+ million three-year reliability and resiliency project will further strengthen the electric grid across Long Island and in the Rockaways. In response to Hurricane Sandy, LIPA and National Grid (the previous service provider to LIPA) acquired funds from FEMA under the FEMA 406 Mitigation program to implement a Hazard Mitigation Program to the LIPA transmission and distribution system. The primary focus of the Program is to harden Long Island’s Transmission and Distribution system by upgrading approximately 450 miles of mainline distribution lines. This is an effort to resist future storm damage and gain a 20% reduction in the number of customers impacted by service interruptions when storm damage occurs.

Project Details

Greenport Energy

Greenport Energy

Village of Greenport

Greenport Energy is a 54-Megawatt, simple cycle combustion turbine generating facility located in the Village of Greenport on the eastern end of Long Island, NY. The project, a Pratt-Whitney FT-8 Swift-Pac system, is under long-term contract to provide capacity, energy, and ancillary services to the Long Island Power Authority.

Project Details

T-Mobile LI-13-506 Transmission Tower Replacement/Cell Site

T-Mobile LI-13-506 Transmission Tower Replacement/Cell Site

T-Mobile

This project was designed to create a new T-Mobile cell site that included all of T-Mobile’s latest cell technologies and required replacement of a 135-foot LIPA transmission tower SP#2085, which supports two 138kV transmission circuits on it. All of the tower work and the high cell site work had to be coordinated, performed and tested during LIPA/PSEG transmission circuit clearances. Ground work included construction of an 11’ x 30’ enclosure housing the cell site compound equipment inside.

Project Details

Gemma Liberty/Patriot – 600MW Power Plants

Gemma Liberty/Patriot – 600MW Power Plants

ABB Cable

Gemma is in the process of constructing two new power plants in North Central Pennsylvania. Our portion of the work consisted of the installation of six 230kV underground power cables at each of the plants. The work included the installation of the cables and twelve terminations, the installation of the ground system and shield limiters. The cable system was a directly buried system and a thermal concrete encapsulated the cables for heat transfer and mechanical protection. The plants will bring additional power to the area, and connects to the Eastern Power grid.

Project Details

Section 105 Rebuild - Old Orchard Beach, Maine

Section 105 Rebuild - Old Orchard Beach, Maine

Iberdrola – Central Maine Power

Rebuild existing 34kV to 69kV standards, including but not limited to: install conductors, overhead shield wires (OHSW), fiber optic ground wire (OPGW) and All Dielectric Self-Supporting Fiber Optic Cable (ADSS). The scope of work includes the pulling, splicing and testing of underground ADSS into the remote end substations via existing underground conduits and inner-duct.

Project Details

CMP Ludden Lane Substation Construction

CMP Ludden Lane Substation Construction

Central Maine Power

We supported construction of a Greenfield substation to support two wind farm developments. The Greenfield Ludden Lane substation work includes construction of approximately 1,000 feet of 115kV transmission lines, tubular steel terminal structures, a substation control enclosure, and installation of various electric transmission system protective devices, including air break switches, SF6 circuit breakers, disconnect switches, motor operators, instrument transformers and related sensing and communication devices.

Project Details

230kV HPFF System Infrastructure to Support PSEG Southern Reinforcement Project

230kV HPFF System Infrastructure to Support PSEG Southern Reinforcement Project

PSEG

Haugland Energy was contracted to install 17,000 linear feet of 8-inch and 6-inch steel pipe for underground HPFF transmission cable as part of PSEG’s Southern Reinforcement Project for the southern New Jersey, additionally, the installation of 4 inch Stainless Steel pipes for a three circuit cross over cabinet. The full project was also completed on-time and on-budget.

Project Details

Norwood 115kV Transmission Line Replacement

Norwood 115kV Transmission Line Replacement

Norwood Municipal Light Department, Norwood MA

This project includes the installation and removal of two 115kV transmission through wetlands and ledge conditions. Construction of 6.4 miles circuit miles of conductor, OPGW and H-Frame wood structures were completed at 75 locations. Our environmental crews managed and installed 7,000 timber matts and cleared three miles of right-of-way, then installed environmental controls throughout the right-of-way, led by our in-house erosion control specialist.

Project Details

Orchard Substation Expansion

Orchard Substation Expansion

Glen Cove, New York

The PSEGLI Orchard Substation expansion required Haugland Energy to install 69kV underground transmission, 15kV underground distribution and 69kV overhead transmission. We were also tasked to complete drainage installation, grading and landscaping of wet meadow area in twelve weeks with an eight-person crew.

Project Details

Dielectric 230kV Underground Cable and Terminations Moxie Liberty and Patriot Projects

Dielectric 230kV Underground Cable and Terminations Moxie Liberty and Patriot Projects

ABB Cable

Gemma Power System is undergoing construction of two new power plants in North Central Pennsylvania. Haugland Energy installed six 230kV underground power cables at each of the plants. Our work included the installation of the cables and twelve terminations, installation of the ground system and shield limiters. The cable system was a directly buried system, and a thermal concrete encapsulated the cables for heat transfer and mechanical protection. The plants will bring additional power to the area and connects to the Eastern Power grid.

Project Details

Cable-In-Conduit (CIC) Installation, Pull Boxes and Related Work

Cable-In-Conduit (CIC) Installation, Pull Boxes and Related Work

Eversource Energy – NSTAR

Installation of approximately 26,165 feet of two-inch Cable-In-Conduit, utilizing Horizontal Directional Drilling (HDD) technology of four NSTAR service territories located in Cape Cod, MA. Work included all required fiberglass, and/or concrete pull boxes, single-phase switching stations, grounding, bond frames, temporary and permanent restoration. The project was performed at four locations in Cape Cod, Massachusetts in the NSTAR service territory.

Project Details

NSTAR – Bourne Substation Cable Installation

NSTAR – Bourne Substation Cable Installation

LS Cable

NSATR built a new switching station that required the installation of a double 230kV underground power cable, a spare cable and a new SF6 breaker. Our scope of work consisted of the installation of seven cables totaling 6,500 feet, seven terminations at one end and SF6 terminations at the far end. The cable system was a directly buried cable system, with a thermal sand back fill. The new switching station allows NSTAR to rearrange the overhead cable system and to add new lines to the system.

Project Details

Far Rockaway Re-Route of 33 and 69kV Cable Circuits

Far Rockaway Re-Route of 33 and 69kV Cable Circuits

National Grid

Haugland Energy installed of 34 poles of various lengths for the relocation of 33kV and 69kV circuits. Due to six feet of flooding at the Substation caused by Superstorm Sandy, the switchgear needed to be bypassed. In addition to the poles, work included the stringing of new lines, four disconnect switches, and breakers.

Project Details

34.5kV Overhead Transmission Construction Rebuild Sections 48, 5A, 187 & 172

34.5kV Overhead Transmission Construction Rebuild Sections 48, 5A, 187 & 172

Ibedrola USA - Central Maine Power

The phased demolition and rebuilding of four separate 34.5kV overhead electric transmission circuits was completed in 22 months, and included approximately 32 miles of single circuit 34.5kV conductor with fiber under build, that utilize direct embedded guyed and un-guyed wood poles, as well as self-supporting single steel pole structures with deep drilled shaft concrete foundations.

Project Details


Line 3128X / #3133 Circuit Tie

Eversource

This project involved the installation of 100 sections of 35kV spacer cable, transferring existing transformers and installing secondary cable. Haugland Energy linemen are specifically trained in the practice rubber gloving voltages up to, and including, 35kV.

Project Details

PSNH Line 388 Overload Solution

Eversource

We were tasked with alleviating the overload on the overhead and underground distribution system on Line 388 in Manchester NH. This was accomplished by installing new 50-foot poles and building a 35-section express spacer cable feeder through double circuit poles in a congested city environment. Our underground crews installed 500 mcm of solid dielectric cables through fifteen manholes and made 35kV splices and terminations.

Project Details

Indian Point Termination Repair and Overhead Line Inspection

Entergy

Entergy has a bi-yearly outage at each of the nuclear power units, when electrical testing is conducted and maintenance is performed on switches, breakers, lightening arresters, current and potential transformers. Additionally, cleaning and inspection of insulators, at both the Entergy yard and Buchannan Substation is completed. Our scope of work included the replacement of gaskets, oil seals, and leak repairs on lead wipes on six 138kV XLPE cable terminations.

Project Details

PSNH Line 3750 Partial Rebuild

Eversource

We rebuilt approximately two miles of transmission line, while the existing 35kV line remained energized. Haugland crews installed a 21 new structures, single pole, H-Frame and 3-pole dead ends. A new feeder was built around the existing substation, and the wire on the right-of-way was transferred, using the 35kV gloving method. New conductors were installed on a 1000-foot span river crossing, which included coordinating boat traffic State authorities.

Project Details

13.8kV Distribution Feeder Installation

Wakefield Municipal Light and Gas

This project for WMGL required the installation of 15kV Hendrix spacer cable, along with new secondary cable, the transfer/replacement of existing equipment, and the replacement of 60 guyed and un-guyed wooden poles. During the phased demolition, the existing circuit needed to remain energized, and customer outages were prohibited.

Project Details

PSNH Power Street URD Replacement

Eversource

Installation of approximately 2,200 feet of 3ph underground cable, and removal of existing overhead pole line. This project includes the excavation and installation of 2,200 feet of conduit, and the splicing and terminating of the 35kV medium voltage cable. Haugland Energy overhead crews also installed riser poles and overhead lateral feeds to the existing circuits.

Project Details

Indian Point 3R10 Switchyard PM's and Correctives

Entergy

Entergy required replacement of a 345kV setup transformer outside of the power plant. Haugland Energy's portion of the project included preforming PM's on four 138kV ground switches and two 138kV disconnect switches, located in the 138kV yard located in the protected area. Haugland Energy performed the removal and installation of two sets of 345kV bus links in the protected area

Project Details

Inspection of HPFF Circuits and Manholes

U.S. Power Generation Astoria

Inspection of Astoria Generating Company’s 138kV High Pressure Fluid Filled (HPFF) feeders 23161 and 23162, and manholes 70830 and 70832. These cables connect the Narrows Generating Facility to Con Edison’s Greenwood substation. The work included photos of the pipes within the manholes, depth gauge of areas on the pipes, and removing loose coating for hidden damage evaluation.

Project Details

No items were found matching your selected filter(s).