Projects Index

Project Index

The Haugland Group has experience working with a wide variety of clients on a diverse range of project types. Some of our recent projects are listed below. Click on “Project Details” to learn more about that projects budget, scope, and other details.


FEMA Long Island Electric Distribution Storm Hardening

FEMA Long Island Electric Distribution Storm Hardening

PSEG Long Island

This $100+ million three-year reliability and resiliency project will further strengthen the electric grid across Long Island and in the Rockaways. In response to Hurricane Sandy, LIPA and National Grid (the previous service provider to LIPA) acquired funds from FEMA under the FEMA 406 Mitigation program to implement a Hazard Mitigation Program to the LIPA transmission and distribution system. The primary focus of the Program is to harden Long Island’s Transmission and Distribution system by upgrading approximately 450 miles of mainline distribution lines. This is an effort to resist future storm damage and gain a 20% reduction in the number of customers impacted by service interruptions when storm damage occurs.

Project Details

Rockaway Boardwalk Reconstruction

Rockaway Boardwalk Reconstruction

Rockaway, New York

In overcoming the devastation of Hurricane Sandy, Grace Industries was assigned the task of restoring the Rockaways. Grace Industries, to date, has been awarded 19 contracts at the Rockaway Boardwalk project spread out over five phases. The project site spans 4.7 miles and comprises of the beaches, boardwalks, and adjacent DPR property lines. Our expertise is required in repairing the damage the storm has left behind and establishing new protective measures. This includes more durable structures and dunes capable of withstanding the strong forces of incoming storms to prevent excessive damage from future natural disasters.

Project Details

Route 347 Reconstruction Mount Pleasant Road to Terry Road

Route 347 Reconstruction Mount Pleasant Road to Terry Road

Smithtown, New York

Reconstruction of Road – The reconstruction of Route 347 includes widening the road and repaving it once all of the drainage system has been installed. The widening will occur on the eastbound and westbound sides of Route 347 along with Terry Road. This is due to an anticipated growth in traffic density in the Smithtown/Hauppauge area.

Project Details

RT 110 Interchange Reconstruction and Widening

RT 110 Interchange Reconstruction and Widening

New York State Department of Transportation

This $55+ million reconstruction and widening project encompassed signal, drainage, safety, and capacity improvements to the Northern State Parkway Bridge over route 110 in Melville, NY. This project is the second phase of a series of 3 projects which, upon completion, will widen Route 110 through a critical, heavily travelled corridor between the Long Island Expressway and the Northern State Parkway.

Project Details

Greenport Energy

Greenport Energy

Village of Greenport

Greenport Energy is a 54-Megawatt, simple cycle combustion turbine generating facility located in the Village of Greenport on the eastern end of Long Island, NY. The project, a Pratt-Whitney FT-8 Swift-Pac system, is under long-term contract to provide capacity, energy, and ancillary services to the Long Island Power Authority.

Project Details

Long Beach Boardwalk Reconstruction

Long Beach Boardwalk Reconstruction

City of Long Beach

The scope of this $44 million project called for the reconstruction of the iconic Long Beach Boardwalk. The 2.2 mile long boardwalk was destroyed by super storm Sandy. This 200-day fast tracked project is on time and on budget.

Project Details


C.R. 67 Motor Parkway Bridge

C.R. 67 Motor Parkway Bridge

Suffolk County

This project called for the reconstruction of CR-67 bridge over the Long Island Expressway. Approaching the project with efficiency and innovation in mind, we consolidated this 3-stage project into 2-stages by eliminating a sidewalk and securing a taxi service for pedestrians. We also capitalized on a changed condition from the Owner allowing us to advance our project through the winter, in turn minimizing project cost.

Project Details

Replacement of Shore Road Circle Bridge Over Amtrak

Replacement of Shore Road Circle Bridge Over Amtrak

New York City Department of Transportation

This multi-million dollar project called for the replacement of the Shore Road Circle Bridge over Amtrak including the deck, abutments, joint materials, structural concrete, rebar, bearings, curtain walls, and all associated items required for a complete replacement. We also performed landscaping, fencing, demolition of existing abandoned substructures, and removal and proper disposal of hazardous materials.

Project Details

Bronx River Greenway, Rehabilitation of Starlight Park

Bronx River Greenway, Rehabilitation of Starlight Park

New York State Department of Transportation

Over the course of this multi-disciplined two year project we were responsible for the installation of a new pedestrian bridge, grading, demolition, pavement, sidewalks, curbs, drainage, lighting, fencing, retaining walls, landscaping, precast bleachers, artificial turf for a soccer/baseball field, basketball court, fountain, playground, and picnic area.

Project Details

Ocean Parkway Viaduct Rehabilitation - Phase II Brighton Line (BMT)

Ocean Parkway Viaduct Rehabilitation - Phase II Brighton Line (BMT)

Metropolitan Transit Authority

The scope of this million dollar project included repairing six existing columns and abutments by removing deteriorated concrete and replacing it with new rebar and concrete. It also called for us to repair spandrel beams and transverse girder encasement. Additionally, we removed, replaced, and restored the deteriorated architectural finish on the viaduct façade and soffit to its original condition.

Project Details

Route 347 Reconstruction

Route 347 Reconstruction

New York State Department of Transportation

This $26.8 million dollar contract required us to reconstruct and widen Route 347 including new asphalt paving, drainage, signal improvements, safety and capacity improvements. Our innovative approach to the project included relocating a proposed water main from the right travel lane to the shoulder which resulted in reduction of night closures and working under traffic, accelerating the project schedule and reducing project costs.

Project Details

Resurfacing of Route 684

Resurfacing of Route 684

New York State Department of Transportation

For this multi-million project we were tasked with cracking and seating the existing concrete pavement while providing a 7-inch asphalt overlay on a 5-mile stretch of roadway. Additionally, it required the installation of under drain on all four shoulders and the extension of the ITS system for the State of New York.

Project Details

Gemma Liberty/Patriot – 600MW Power Plants

Gemma Liberty/Patriot – 600MW Power Plants

ABB Cable

Gemma is in the process of construction two new power plants in North Central Pennsylvania our portion of the work consisted of the installation of 6 - 230 kV underground power cables at each of the plants. The work included the installation of the cables and 12 terminations, installation of the ground system and shield limiters.

Project Details

Section 105 Rebuild - Old Orchard Beach, Maine

Section 105 Rebuild - Old Orchard Beach, Maine

Iberdrola – Central Maine Power

Rebuild existing 34kV to 69kV Standards including but not limited to: Install conductors, overhead shield wires (OHSW), fiber optic ground wire (OPGW) and All Dielectric Self-Supporting Fiber Optic Cable (ADSS) Includes pulling, splicing, and testing of underground ADSS into the remote end substations via existing underground conduits and inner-duct.

Project Details

City of Long Beach Comfort Stations

City of Long Beach Comfort Stations

City of Long Beach NY

Grace Industries, LLC performed the construction of five elevated Comfort Stations along the Long Beach Boardwalk to replace bathrooms which were heavily damaged during Superstorm Sandy. The work included construction of pile supported cast-in-place concrete foundations. The bathroom structures were prefabricated concrete units assembled using a crane at each location.

Project Details

CMP Ludden Lane Substation Construction

CMP Ludden Lane Substation Construction

Central Maine Power

The Ludden Lane project is for the construction of the Greenfield Ludden Lane Substation. The work includes construction of approximately 1000 feet of 115kV transmission lines, tubular steel terminal structures, a substation control enclosure, and installation of various electric transmission system protective devices such as air break switches, SF6 circuit breakers, disconnect switches, motor operators, instrument transformers and related sensing and communication devices.

Project Details


230kV HPFF System Infrastructure to Support PSEG Southern Reinforcement Project

230kV HPFF System Infrastructure to Support PSEG Southern Reinforcement Project

PSEG

Haugland Energy (HE) was contracted to install 17,000 linear feet of 8” and 6” steel pipe for underground HPFF transmission cable as part of PSEG’s Southern Reinforcement Project for the southern New Jersey. In-addition the installation of 4” Stainless Steel pipes for a three circuit cross over cabinet. The full project was also completed on-time and on-budget.

Project Details

Norwood 115kV Transmission Line Replacement

Norwood 115kV Transmission Line Replacement

Norwood Municipal Light Department, Norwood MA

This project includes the installation and removal of two 115kV transmission through wetlands and ledge conditions. The work involves construction of 6.4 miles circuit miles of conductor, OPGW and H-Frame wood structures at 75 locations.

Project Details

Orchard Substation Expansion

Orchard Substation Expansion

Glen Cove, New York

This project for PSEGLI Orchard Substation expansion required Haugland Energy to install 69kv Underground transmission, 15kv underground distribution and 69kv overhead transmission and to complete drainage installation, grading and landscaping of Wet Meadow area in 12 weeks with a 8 person crew.

Project Details


Cable-In-Conduit (CIC) Installation, Pull Boxes, and Related Work

Cable-In-Conduit (CIC) Installation, Pull Boxes, and Related Work

Eversource Energy – NSTAR

Installation of approximately 26,165’ of 2” Cable-In-Conduit utilizing Horizontal Directional Drilling (HDD) technology of four NSTAR service territories located in Cape Cod, MA. Work included all required fiberglass and or concrete pull boxes, single phase switching stations, grounding, bond frames, temporary and permanent restoration.

Project Details

NSTAR – Bourne Substation Cable Installation

NSTAR – Bourne Substation Cable Installation

LS Cable

NSTAR built a new switching station that required the installation of a double 230 kV underground power cable plus a spare cable and a new SF6 breaker. Our portion of the work consisted of the installation of 7 cables totaling 6,500 feet, 7 terminations at one end and SF6 terminations at the far end.

Project Details

Far Rockaway Re-Route of 33 and 69kV Cable Circuits

Far Rockaway Re-Route of 33 and 69kV Cable Circuits

National Grid

The project was for the installation of 34 poles ranging of various lengths for the relocation of 33 kV and 69 kV circuits. Due to six feet of flooding at the Substation caused by Hurricane Sandy, the switchgear needed to be bypassed. In addition to the poles the work included the stringing of new lines, four disconnect switches and breakers.

Project Details

34.5kV Overhead Transmission Construction Rebuild Sec 48, 5A, 187 & 172

34.5kV Overhead Transmission Construction Rebuild Sec 48, 5A, 187 & 172

Ibedrola USA - Central Maine Power

This project for Central Maine Power requires the phased demolition and rebuilding of four separate 34.5kV overhead electric transmission circuits in 22 months. The work consisted of approximately 32 miles of single circuit 34.5kV conductor with fiber under build that utilize direct embedded guyed and un-guyed wood poles as well as self-supporting single steel pole structures with deep drilled shaft concrete foundations.

Project Details


Line 3128X / #3133 Circuit Tie

Eversource

This project involves the installation of 100 sections of 35kv spacer cable and also includes transferring existing transformers and installing secondary cable. Haugland Energy linemen are specifically trained in the practice rubber gloving voltages up to and including 35 kv.

Project Details

Northern State Parkway Repaving

New York State Department of Transportation

This multi-million dollar project called for the repaving of sixteen miles of the Northern State Parkway stretching from Route 110 to Happauge. We approached this project with value engineering in mind, utilizing 2 RoadTec 900x on the 25-feet wide roadway, which enabled us to mill both lanes simultaneously. We also utilized Michigan wedge pavement joints to eliminate the need to back up and square up the new paving each night, which increased our productivity resulting in an expedited project schedule and a reduction in project cost.

Project Details

PSNH Line 388 Overload Solution

Eversource

The purpose of this project was to alleviate the overload on the overhead and underground distribution system on Line 388 in Manchester NH. We did this by installing new 50 ft. poles and building a 35 section express spacer cable feeder through double circuit poles in a congested city environment.

Project Details

Indian Point Termination Repair and Overhead Line Inspection

Entergy

Entergy has a bi-yearly outage on each of the nuclear power units, which electrical testing is conducted and maintenance of switches, breakers, lightening arresters, current and potential transformers, in addition cleaning and inspection of insulators, at both the Entergy yard and Buchannan Substation. Our work included the replacement of gaskets, oil seals, and leak repairs on lead wipes on Six 138 kV XLPE cable terminations.

Project Details

PSNH Line 3750 Partial Rebuild

Eversource

This project was the rebuild of approx. 2 miles of transmission line while the existing 35 kv line remained energized. Haugland crews installed a 21 new structures, single pole, H-Frame and 3-pole dead ends. A new feeder built around the existing substation, and the wire on the right of way was transferred using the 35kv gloving method. New conductors were installed on a 1000 ft. span river crossing which included coordinating boat traffic the State Authorities.

Project Details

13.8kV Distribution Feeder Installation

Wakefield Municipal Light and Gas

This project for WMGL required the installation of 15kV Hendrix spacer cable along with new secondary cable, the transfer/replacement of existing equipment and the replacement of 60 guyed & un-guyed wooden poles. During the phased demolition, the existing circuit had to remain energized and customer outages were prohibited.

Project Details

PSNH Power Street URD Replacement

Eversource

Installation of approx. 2200ft of 3ph underground cable and removal of existing overhead pole line. This project includes the excavation and installation of 2200 feet of conduit, and the splicing and terminating of the 35kv medium voltage cable. Haugland Energy overhead crews also installed riser poles and overhead lateral feeds to the existing circuits.

Project Details

Indian Point 3R10 Switchyard PMs and Correctives

Entergy

Entergy required replacement of a 345 kv setup transformer outside of the power plant. Haugland Energy's portion of the project included preforming PM's on four 138KV ground switches and two 138KV disconnect switches located in the 138KV yard located in the Protected Area. In addition they performed the removal and installation of two sets of 345KV bus links in the Protected area.

Project Details

Inspection of HPFF Circuits and Manholes

U.S. Power Generation Astoria

This project was for the inspection of Astoria Generating Company’s 138kV High Pressure Fluid Filled (HPFF) feeders 23161 and 23162 and manholes 70830 and 70832 These cables connect the Narrows Generating Facility to Con Edison’s Greenwood substation.

Project Details

No items were found matching your selected filter(s).